KharkivOblenergo reconstructed power grids in Dergachi and Liubotyn

KharkivOblenergo reconstructed power grids in Dergachi and Liubotyn

08.01.2025 07:15

The JSC KharkivOblenergo has completed projects to reconstruct power lines in Dergachi and Liubotyn as part of its investment programme for 2024.

According to the press service of KharkivOblenergo, a 6 km overhead line was upgraded in Dergachi, which made it possible to ensure a stable power supply in the western part of the city.
"A new transformer and 144 electric poles were installed, as well as new 10 kV and 0.4 kV lines. The key goal of all these measures is to improve the quality of services to consumers and increase the level of reliability of electricity supply," the statement said.
Two 0.4 kV overhead lines were reconstructed in Liubotyn.